Prefabricated & Modularly Constructed Data Center
This project was a turn key delivery of 12 MW of electrical infrastructure with 10 MW’s critical built in 6 months. This high-density, 400W / SF project was deployed alongside other active data centers on the client’s existing campus and optimized to fit the client’s rack deployment technology.
Services Rendered:
- Design Management
- Design Review
- Equipment Procurement
- Construction Management
- IT Integration Management
- Commissioning Management
- White Space Fitout
Project Summary

12 MW DATA CENTER PROJECT

PRE-CAST SHELL

LOADING DOCK AND SUPPORTS PACES

ALL COORDINATION FOR INTEGRATION WITH EXISTING SERVICES OF ANOTHER ACTIVE AND SECURE DATACENTER

6 months construction schedule

6-2 MW ELECTRICAL BLOCKS IN A 6 TO MAKE 5 BLOCK REDUNDANT DESIGN