Hyperscale Colocation Campus for Cloud Clients
This was the first project this client implemented Integra’s modular infrastructure. The Integra design resulted in a 30% reduction in overall project cost and an increase to site density by 40%. Using Integra’s modular infrastructure, we were able to compress the schedule by 2 months.
Services Rendered:
- Design Management
- Design Review
- Equipment Procurement
- Construction Management
- IT Integration Management
- Commissioning Management
- City-County Coordination
Project Summary

28 MW DATA CENTER PROJECT

Eight month construction schedule construction schedule

Peak PUE 1.25
Annualized PUE 1.08
Annualized PUE 1.08

13 MW’s of Electrical Infrastructure, 10 MW’s critical